The new production line project of Skyline Transformer was put into trial production, and the equipment and equipment were upgra

The new production line project of Skyline Transformer was put into trial production, and the equipment and equipment were upgra

Release time:
2014/09/13 14:42
Page view
[Abstract]:
 Zhejiang Skyline Transformer Co., Ltd. has an annual investment of 2 million units of high, medium and low voltage transformer production lines with a total investment of 203 million yuan. Since the

 Zhejiang Skyline Transformer Co., Ltd. has an annual investment of 2 million units of high, medium and low voltage transformer production lines with a total investment of 203 million yuan. Since the official construction began at the end of July last year, the business owners have carefully arranged and built the construction. At present, the main project has been completed, and the 220 kV transformer production workshop has been put into trial production.

In the 220 kV transformer production workshop, the reporter discovered a fully shielded laboratory built by Skyline. The laboratory is 18 meters high and covers an area of ​​600 square meters with a total investment of 27 million yuan.
Reporter: As soon as we walked in, we found that it was very empty. Everyone looked at this large equipment behind me. According to the technician, it is ten meters high. Its function is to detect the partial discharge and withstand voltage of the finished transformer. Insulation performance. This is also the only fully shielded test hall in the province with a detection capability of 220 kV transformers.
Xu Wen, the person in charge of Zhejiang Skyline Transformer Co., Ltd.: Our company has made a six-sided fully shielded test room, which can isolate all the electromagnetic signals from the outside world, so that our 600 kV corona-free test transformer can detect more accurately. Some partial discharge and power frequency withstand voltage indicators of our transformers make the performance of the products more secure and reliable.

天际互感

天际互感

 In addition to the fully shielded test room, we also saw a lot of automation equipment in the 220 kV transformer production workshop, including fully automatic insulation wrap machine, full vacuum drying system, full vacuum oil filling system, etc. The entire workshop achieved full closure production. The person in charge of the company told the reporter that the total investment of the whole workshop has reached more than 45 million yuan. After all the equipments are put into operation, the production efficiency of the enterprise will be greatly improved.

Tang Fuxin, deputy general manager of Zhejiang Skyline Transformer Co., Ltd.: The products produced in this workshop are the production workshops with the highest performance requirements of our company. In this workshop, we only have 50 workers to complete 4,000 units per year (inductance). There is a production capacity of 80 million.
 
At present, the remaining four buildings of the entire project have entered the stage of internal decoration and equipment commissioning, and it is planned to be put into production before the Spring Festival.
Tang Fuxin, deputy general manager of Zhejiang Skyline Transformer Co., Ltd.: The successful implementation of this project has enabled our company to have a production capacity of 0.38 kV to 220 kV, and has the production target of 2 million high, medium and low voltage transformers per year. Our company has entered the ranks of leading enterprises in the transformer industry.